[quote=flu][quote=Arraya]BBC is now reporting a whistleblower statement by Masashi Goto, nuclear engineer, that Toshiba (plant builder) knew that the engineering specs were not adequate for a disaster of this magnitude. Looks like this is a classic cost-benefit scenario, where engineers tell management what is necessary, and management makes the decision about the risks they can live with – in order to get the project margin up.[/quote]
Well, the interesting part though is that Toshiba didn’t build all three reactors…
Unit No. 1 is a General Electric Co. (GE) model that can generate 439 megawatts of power and began commercial operation in 1971, according to the International Atomic Energy Agency. The No. 2 reactor was built by GE Toshiba and the No. 3 by Toshiba Corp.
I doubt anyone really planned for a 9.0 earthquake followed by a tsunami that would cut off backup power, and backup to backup power to the cooling systems…[/quote]
1431: More from Japanese nuclear engineer Masashi Goto: He say that as the reactor uses mox (mixed oxide) fuel, the melting point is lower than that of conventional fuel. Should a meltdown and an explosion occur, he says, plutonium could be spread over an area up to twice as far as estimated for a conventional nuclear fuel explosion. The next 24 hours are critical, he says.
1426: Mr Goto says his greatest fear is that blasts at number 3 and number 1 reactors may have damaged the steel casing of the containment vessel designed to stop radioactive material escaping into the atmosphere. More to follow.
1422: Japanese engineer Masashi Goto, who helped design the containment vessel for Fukushima’s reactor core, says the design was not enough to withstand earthquakes or tsunamis and the plant’s builders, Toshiba, knew this. More on Mr Goto’s remarks to follow.